LMD expands phase 1 of build out from 25 to 45 MW
Lefdal Mine Datacenter recently decided to increase the build out of phase 1 from 25 to 45 MW. The planned backbone of the cooling infrastructure and the usable floor space has been expanded accordingly.
This means a prolonging of the construction process, moving the opening of the facility to May 2017.
The picture shows the first pipes lowered into place.